Functional Verification Resource Puzzle
Two functional verification servers, A and B, are processing a massive test regression suite. Server A working alone takes 12 hours to finish the suite. Server B working alone takes 24 hours. They start processing the suite together at the same time. However, after 4 hours, Server A crashes. How many additional hours will it take Server B, working alone, to finish the remaining tests in the suite?